About The Project
Name of Project: HOT ASPHALT PAVEMENT IN MISCELLANEOUS LOCATIONS OF KAYSERI
Place of Project: Kayseri, Turkey
Administration: METROPOLITAN MUNICIPALITY OF KAYSERI
Date of Completion: May, 2016
Duration of Project: 350 days
Description: Project consists of 43 components. Within the scope of the Project, mainly 60,000 tons of Stone Mastic Asphalt (SMA) and 120,000 tons of Hot Bituminous Mixture (HBM) Pavement Works were done.